These are the questions landlords, managing agents and tenants ask most about solar panels for industrial units. They are grouped by the decision they belong to: the lease, the roof, the grid, tax and the process. For the full landlord-and-tenant picture, read the guide to landlord consent for solar on an industrial unit. If your question is not here, send an enquiry and we reply by email.

Lease and consent

Do I need landlord consent for solar on an industrial unit?

Usually yes. Fitting panels is normally an alteration to the roof, which most leases make a matter for the landlord’s written consent. Some leases bar it. Read the alterations clause, and see the guide to solar panels on a rented industrial unit for the full position.

Who pays for solar on a multi-let estate, the landlord or the tenant?

Either, or a third party. The lease and the route decide. A tenant can buy for its own unit with consent, a landlord can buy and share the benefit on terms set in the lease, or a third-party owner can fund it. A landlord can recover the cost through the service charge only if the lease allows it.

Should we own the system or use a power purchase agreement?

Owning means you claim the allowances and keep the saving; a PPA means someone else owns it. Under a power purchase agreement a third party owns and runs the panels and you pay for the power you use, usually with no upfront cost. Compare the term, the price per kWh and the end-of-term options. A PPA is often considered by tenants on shorter leases; an owner-occupier has more reason to buy.

What happens to the panels at the end of the lease?

A clause should settle it before installation. The options are removal by the tenant with the roof made good, transfer to the landlord on agreed terms, or continuation under a PPA with a successor. The Better Buildings Partnership Green Lease Toolkit is a useful starting point for the wording.

Roof and output

Can an industrial unit run entirely on solar?

Not from panels alone. Panels only produce in daylight and output varies with the season and the weather, so the grid supplies the rest. A system sized to the daytime load is the normal aim. A battery can move some output into the evening.

What happens to solar power at night on an industrial unit?

Nothing is generated, so the unit draws from the grid or from a battery if one is fitted. Surplus exported in the daytime can earn payments under the Smart Export Guarantee if your supplier offers a tariff. Rates are set by each supplier, so compare them.

Will my roof take solar panels?

It depends on the covering and the structure. Profiled metal, insulated sandwich panel, standing seam, fibre-cement and flat membrane roofs each need different fixings. A fibre-cement roof needs an asbestos check first. A structural engineer should confirm the loading, and the roof warranty and the landlord’s insurer should be checked before anything is fixed.

Grid and planning

Do I need the network operator’s permission?

A G98 notification can apply up to 16 A per phase; above that you need a G99 application. 16 A per phase is about 3.68 kW on a single phase and about 11 kW on three phases. Above those limits the network operator must approve the connection before the array is connected.

Do I need planning permission?

Often not, but the route depends on the nation. England uses Class J of Part 14 (prior approval for arrays above the 50 kW microgeneration scale; listed buildings and scheduled monuments excluded), Wales uses Part 43 Class A and Scotland uses Class 6J. Northern Ireland has its own rules.

Tax and rates

Can a tenant claim capital allowances on solar?

Yes, if the tenant pays for the panels and holds an interest in the land. A lease counts as an interest in land. Only one person can claim for the same fixture, so agree who in writing. Solar PV is special-rate plant: the annual investment allowance (£1 million a year) can give 100% relief in year one if there is room under the limit, and companies can claim a 50% first-year allowance above it.

Do business rates go up when panels are fitted?

In England, solar generating plant is left out of the rateable value until 31 March 2035. That comes from SI 2022/405 and applies in England only. It does not apply in Wales, Scotland or Northern Ireland.

What about Freeport sites?

Only inside a designated Freeport tax site. Companies buying new plant and machinery for primary use there can claim a 100% first-year allowance. It does not apply to every building in the same city or region, and it is clawed back if the asset leaves primary use in a tax site within five years. English relief runs to 30 September 2031. Check the tax-site boundaries on GOV.UK.

Process

How long does it take to install solar on an industrial unit?

There is no single figure we can source. The work on the roof is usually the shorter part. Consent, design, the grid application and any structural work come first and set the elapsed time. Ask any installer for a written programme.

What happens when I send my details?

We reply by email. Your details go to SEO Dons Ltd, the publisher of this guide. We are not an installer. We never sell your details.

Get a free solar quote for your industrial unit